Hoa Binh 1,2 (2 phase) wind farm project.

Location: Hoa Binh, Bac Lieu Province, Viet Nam
Scope of work: 

Piling works PHC D800/60-70m (From March/2020 to October/2020)

total: 30,000md
Equipment’s Used:
1. Barge/crane: 3600 tons/200 ton, diesel hammer 10 ton…

2. Barge/crane: 9000 tons/250 ton, diesel hammer 10 ton…

3. Barge/crane: 1800 tons/150 ton, diesel hammer 10 ton…